Heritage Cases

THIS IS THE ARCHIVE FOR SAHRIS 1.0


THIS SITE IS NOW AN ARCHIVE AND IS NOT SUITABLE FOR MAKING APPLICATIONS

Please be aware that no content and application creation or changes to information on this version of SAHRIS will be retained.

To make applications or utilise SAHRIS for the creation of information, please use the new site:

https://sahris.org.za

Changes to SAHRIS!

The South African Heritage Resources Information System (SAHRIS) has undergone a generational upgrade and restructure. These changes to the site include, but are not limited to:

  • A new & modernised look and layout
  • Improved site usage flows with respect to applications and content creation
  • Improved site performance and stability

Launch for the new version of SAHRIS occurred on Monday the 30th of October 2023.

The new site can be found here:

SAHRIS | SAHRIS

SAHRA Application Closure

Please note the following concerning applications submitted to the South African Heritage Resources Agency (SAHRA) during the December 2023 to January 2024 period.

The full notice is available here: Notice

Special Notice

Following comments received on the proposed Revised Schedule of Fees for applications made to the South African Heritage Resources Agency (SAHRA), made in terms of Section 25(2)(l) of the National Heritage Resources Act No. 25 of 1999 (NHRA) and published in the Government Gazette of 22 July 2022, SAHRA hereby publishes the final Revised Schedule of Fees for Applications made to SAHRA. Applications for provision of services submitted to the South African Heritage Resources Authority (SAHRA), in terms of the National Heritage Resources Act, No. 25 of 1999 (NHRA) must be accompanied by a payment of the appropriate fee, taking effect from 1 January 2023

Revised Schedule of Fees for Applications made to the South African Heritage Resources Agency (SAHRA)

Mining Permit Area - Vuurfontein 117 HO

CaseViews

CaseHeader

Status: 

HeritageAuthority(s): 

Development Type: 

ProposalDescription: 

Mining Permit for: Diamonds (Alluvial) (DA) on 5 Ha. The area will be mined through opencast excavations where the diamond gravel will be removed with an excavator or frond end loader onto the tipper trucks and taken to the processing area where it will be put through a washing pan for processing. Rough out of the pan and over size stones will be taken back to the excavation for backfilling and the wet puddle will be pumped directly into open excavations. Diamond gravel will be sorted and recovered by hand.

Expanded_Motivation: 

N J VAN ZYL intends to mine for Diamonds (Alluvial) (DA) situated on the farm VUURFONTEIN 117 HO (over a portion of the Remaining Extent of Portion 13), Bloemhof district and 5 hectares in total. See location of application area. The alluvial diamond gravel will be mined over the whole of the application area. The gravel is on average 2.5 meter thick with a topsoil layer which varies between 1000 and 1500 millimeters. The area that was identified and demarcated is shown on the Sketch plan. The gravel reserve on these 5 hectares is estimated at 50’000m³ or ± 56’650 tons and the total material to be moved is 50’000m³. The above area will be mined through opencast excavations where the topsoil will be stripped separately and stockpiled. The gravel is then removed with a 30-ton excavator and placed next to the excavation. A Front -end Loader takes the gravel to the 14 feet washing pan which is fed at a rate of 10m³ an hour, 48m³ a day and 4800m³ a month. All the rough are first placed back into the bottom of the excavation, hereafter the puddle out of the pan is pumped directly back into the open excavation. After the puddle dried off, the topsoil is put back on top again. The excavations will be 60m in length 10m wide and ±2,5 meters deep on average. Four excavations will be opened at any given time. The total estimated reserve of gravel is 50’000m³ taken at a production rate of 48’00m³ a month it will take 24 months to work the estimated reserve of ±50’000m³. The production rate is taken at 4’800m³/month. The gravel which is relatively shallow (2,5 meter) and the low production rate of the applicant make this 5 hectare to be worked sustainable over a period of two years.

ApplicationDate: 

Thursday, October 26, 2023 - 13:32

CaseID: 

22810

OtherReferences: 

CaseReferenceDepartmentApplicationTypeDeadlineDateContactPerson
NW30/5/1/3/2/11231 MP
26/11/2023

ReferenceList: 

 
 

Search form